Publications personnelle

73documents trouvés

08224
09/07/2008

A cooperative approach for job shop scheduling under uncertainties

C.BRIAND, S.OURARI, B.BOUZOUIA

MOGISA, CDTA d'Alger

Manifestation avec acte : International Conference on Collaborative Decision Making (CDM'08), Toulouse (France), 1-4 Juillet 2008, pp.5-15 , N° 08224

Diffusable

Plus d'informations

Mots-Clés / Keywords
Cooperative scheduling; Flexibility; Robustness; Dominance;

114299
08244
19/05/2008

Activity insertion problem in a RCPSP with minimum and maximum time lags

C.ARTIGUES, C.BRIAND

MOGISA

Ouvrage (contribution) : Resource-constrained project scheduling. Models, algorithms, extensions and applications, ISTE/Wiley, Eds. C.Artigues, S.Demassey, E.Neron, N°ISBN 978-1-84821-034-9, Mai 2008, Chapitre 11, pp.171-190 , N° 08244

Non diffusable

113826
08194
01/03/2008

Une approche coopérative pour l'ordonnancement sous incertitudes

C.BRIAND, S.OURARI, B.BOUZOUIA

MOGISA, CDTA d'Alger

Manifestation avec acte : 7ème Conférence Internationale de Modélisation et Simulation (MOSIM'08), Paris (France), 31 Mars - 2 Avril 2008, 8p. , N° 08194

Diffusable

Plus d'informations

Résumé

Cet article s'intéresse aux problèmes d'ordonnancement de type job shop. Contrairement aux approches classiques, on suppose que les travaux à réaliser ne sont pas tous connus initialement et qu'ils sont définis au fur et à mesure que les commandes apparaissent, l'ordonnancement étant alors adapté de façon réactive. Le fait que l'approche dordonnancement proposée dans cet article soit coopérative constitue une deuxième originalité. Chaque ressource gère son propre ordonnancement local (ordonnancement à une machine), l'ordonnancement global résultant d'une coopération entre les diverses ressources. On suppose que les ordonnancements locaux sont des ordonnancements incorporant de la flexibilité séquentielle, cette flexibilité permettant d'une part à chaque ressource de négocier avec les autres et, d'autre part, de faire face aux incertitudes liées à la mise en oeuvre. Lobjectif global recherché est la cohérence des décisions prises sur chaque ressource avec maintien dun niveau de flexibilité donné. Pour cela, un modèle est défini et des mécanismes de coopération entre ressources, permettant la négociation de décision d'ordonnancement, sont proposés.

Mots-Clés / Keywords
Ordonnancement coopératif; Job shop; Robustesse; Dominance;

113556
08195
01/02/2008

Conditions de dominance pour le problème à une machine avec minimisation des travaux en retard

S.OURARI, C.BRIAND

MOGISA, CDTA d'Alger

Manifestation avec acte : 9ème Congrès de la Société Française de Recherche Opérationnelle et d'Aide à la Décision (ROADEF'08), Clermont-Ferrand (France), 25-27Février 2008, pp.351-352 , N° 08195

Diffusable

Plus d'informations

Mots-Clés / Keywords
Ordonnancement; Dominance; Théorème des pyramides; Séquence maître-pyramide;

113558
08055
01/01/2008

Flight training timetabling

C.ARTIGUES, C.BRIAND, P.LOPEZ

MOGISA

Rapport de Contrat : Contrat AIRBUS ST Training, Janvier 2008, 46p. , N° 08055

Non diffusable

113118
07509
01/07/2007

A new dominance condition for mono-pyramidal single machine scheduling problems

C.BRIAND, S.OURARI, B.BOUZOUIA

MOGISA, CDTA d'Alger

Manifestation avec acte : 8th Workshop on Models and Algorithms for Planning and Scheduling Problems (MAPSP'2007), Istanbul (Turquie), 2-6 Juillet 2007, 3p. , N° 07509

Diffusable

112272
07508
01/07/2007

Complexity of activity insertion for resource-constrained project scheduling with minimum and maximum time lags

C.ARTIGUES, C.BRIAND

MOGISA

Manifestation avec acte : 8th Workshop on Models and Algorithms for Planning and Scheduling Problems (MAPSP'2007), Istanbul (Turquie), 2-6 Juillet 2007, 3p. , N° 07508

Diffusable

112273
07490
01/06/2007

A robust approach for the single machine scheduling problem

C.BRIAND, H.T.LA, J.ERSCHLER

MOGISA

Revue Scientifique : Journal of Scheduling, Vol.10, N°3, pp.209-221, Juin 2007 , N° 07490

Diffusable

Plus d'informations

Abstract

This paper describes a robust approach for the single machine scheduling problem 1|r i |L max . The method is said to be robust since it characterizes a large set of optimal solutions allowing to switch from one solution to another, without any performance loss, in order to face potential disruptions which occur during the schedule execution. It is based on a dominance theorem that characterizes a set of dominant sequences, using the interval structure defined by the relative order of the release and the due dates of jobs. The performance of a set of dominant sequences can be determined in polynomial time by computing the most favorable and the most unfavorable sequences associated with each job, with regard to the lateness criterion. A branch and bound procedure is proposed which modifies the interval structure of the problem in order to tighten the dominant set of sequences so that only the optimal sequences are conserved.

Mots-Clés / Keywords
Scheduling; Robustness; Sequential flexibility; Interval structures; Pyramids;

111364
07510
01/06/2007

Vers une approche distribuée pour l'ordonnancement réactif sous incertitudes

S.OURARI, C.BRIAND, B.BOUZOUIA

CDTA d'Alger, MOGISA

Manifestation avec acte : Colloque sur l'Optimisation et les Systèmes d'Information (COSI 2007), Oran (Algérie), Juin 2007, pp.449-460 , N° 07510

Diffusable

Plus d'informations

Résumé

Cet article s'intéresse au problème job shop classique à plusieurs machines, noté Jn»»Cmax. Contrairement aux approches classiques, on suppose que les travaux à réaliser ne sont pas tous connus initialement et qu'ils sont définis au fur et à mesure que les commandes apparaissent, l'ordonnancement étant alors adapté de façon réactive. Le fait que l'approche d'ordonnancement proposée dans cet article soit distribuée constitue une deuxième originalité. Chaque ressource gère son propre ordonnancement local (ordonnancement à une machine), l'ordonnancement global résultant d'une coopération entre les diverses ressources. On suppose que les ordonnancements locaux sont des ordonnancements incorporant de la flexibilité séquentielle, cette flexibilité permettant d'une part à chaque ressource de négocier avec les autres et, d'autre part, de faire face aux incertitudes liées à la mise en oeuvre. L'objectif global recherché est la cohérence des décisions prises sur chaque ressource avec maintien d'un niveau de flexibilité donné. Pour cela, un modèle de contraintes est défini et des mécanismes de coopération entre ressources, permettant la négociation de décision d'ordonnancement, sont proposés.

112271
06221
25/10/2006

Minimizing the number of late jobs in single machine scheduling with nested execution intervals

C.BRIAND, S.OURARI

MOGISA, CDTA d'Alger

Manifestation avec acte : International Conference on Service Systems & Service Management (ICSSSM'06), Troyes (France), 25-27 Octobre 2006, pp.1172-1177 , N° 06221

Diffusable

108765
Pour recevoir une copie des documents, contacter doc@laas.fr en mentionnant le n° de rapport LAAS et votre adresse postale. Signalez tout problème de fonctionnement à sysadmin@laas.fr. http://www.laas.fr/pulman/pulman-isens/web/app.php/